Earned Schedule (ES) is a project management technique that extends the concepts of Earned Value Management (EVM) to schedule performance analysis. It provides a way to forecast project schedule performance based on the rate at which work is completed, as measured by Earned Value (EV).
In traditional Earned Value Management, performance is assessed by comparing the planned value (PV), earned value (EV), and actual cost (AC) of the project at a specific point in time. These metrics are used to calculate various performance indices like Cost Performance Index (CPI) and Schedule Performance Index (SPI). While CPI provides insights into cost performance, SPI focuses on schedule performance.
However, SPI can sometimes be misleading, especially in projects with non-linear work progress or where the duration of work packages varies. Earned Schedule was developed to address this limitation and provide a more accurate representation of schedule performance.
The fundamental concept in Earned Schedule is the use of Earned Schedule indices:
1. Schedule Performance Indicator (SPI(E)): This index indicates the schedule efficiency of the project. It is calculated as follows:
SPI(E) = EV / ES
Where EV is the Earned Value (the value of completed work), and ES is the Earned Schedule (the time by which work should have been completed).
2. Schedule Variance (SV(E)): This metric represents the variance between the Earned Schedule and the Planned Schedule. It shows whether the project is ahead of or behind schedule.
SV(E) = EV - ES
The benefits of Earned Schedule include:
Improved Schedule Performance Analysis: Earned Schedule provides a more accurate and reliable assessment of schedule performance, especially in projects with uneven work distribution.
Early Warning System: By analyzing the Schedule Performance Indicator (SPI(E)) and Schedule Variance (SV(E)), project managers can identify schedule issues earlier and take corrective actions proactively.
Enhanced Forecasting : Earned Schedule allows project managers to forecast the time required to complete the remaining work based on the current performance rate. This aids in better project planning and resource allocation.
Complements Earned Value Management : Earned Schedule doesn't replace traditional Earned Value Management but complements it by providing additional insights into schedule performance.
Overall, Earned Schedule is a valuable tool for project managers to gain a deeper understanding of schedule performance, anticipate potential delays, and make informed decisions to keep the project on track.