top of page

Critical vs. Longest Path and Multiple Float Paths in Primavera P6

Writer's picture: Ali TorkamaniAli Torkamani

In project scheduling, understanding the critical path is essential for any scheduler. A proficient scheduler should thoroughly understand the interconnections within the schedule and the potential impacts of modifications or deviations from the planned sequence. It is equally crucial for the project manager to comprehend the critical path to effectively manage and mitigate associated risks. The critical path is typically defined as a sequence of interconnected activities that dictate the overall duration of a project. Any delays in these activities directly extend the project's completion date. There are two primary ways to identify the critical path in a project network: by using the total float or identifying the longest path. The distinction between these two methods can be significant:


Total Float Method: In Primavera P6, the total float approach allows for the setting of a maximum float threshold for activities before they are considered critical. This threshold could be zero, negative, or positive, and may be calculated based on the finish float, start float, or the lesser of the two.


Longest Path Method: Choosing the longest path method defines the critical path as the longest continuous path through the project schedule, irrespective of any float values.

This differentiation is vital for effective project management, influencing how delays are managed and how potential risks are addressed.


The concept of the longest path can be viewed as a form of critical path; however, not all critical paths are the longest paths. Typically, at the onset of a project, the path with a total float of zero is considered the longest. When you calculate the longest path for a project that includes actual progress, constraints, and deadlines, you often identify a sequence of critical activities that aren't necessarily the longest in terms of duration. Activities with constraints may exhibit negative floats, which can then influence the floats of their successor or predecessor tasks. It is crucial to understand these dynamics when selecting a method to determine the critical path. Ultimately, the choice of method hinges on how you wish to analyze and communicate your schedule. It might also be prudent to calculate multiple float paths to track their evolution over time. Discipline leads might need to be informed of their specific critical paths, so it might be useful to determine the critical path based on the final activity within their discipline. Primavera P6 facilitates the calculation and display of up to 10 float paths, using either free float or total float. The total float method is generally preferable if the calculations need to consider the project's ultimate deadline, as it reflects the project-wide implications. On the other hand, the free float method is better suited when the focus is on understanding disruptions within individual paths, without the need to account for an overall project deadline.


Switch the 'Group By' setting to 'Float Path', enable the display of 'Title' and 'Name/Description', and then click 'Apply'


110 views0 comments

Recent Posts

See All

Comentarios


bottom of page